Iterative
Development Testing Approaches
Managing
Iterative Testing in an Agile Development Project |
|
by
Bryan Campbell and Dr.
Glenn Ray
April
9, 2002 |
| Article
Attributes |
|

|

|
|
|
Microsoft
Word |
Adobe
Acrobat |
|
|
| Abstract |
|
Over
the past five years, there has been increasing interest in
agile development approaches to software development (such as eXtreme
Programming), however, integrating these into a unified testing approach
can be challenging given their rapid delivery environment.
Applying a testing framework to an agile development approach
provides a greater opportunity to ensure a robust and high quality
application. This paper
reviews a web-services software development project completed at the end
of the year 2000 for a large Fortune 500 company.
The project used an object-oriented design and blended the more
formal Rational Unified Process (RUP) with the low ceremony approached
advocated by eXtreme Programming (XP).
The application testing approach applied the unit test framework
of XP with a formal testing methodology required by the client for this
high profile project. The paper describes the process followed and key learnings
discovered throughout the project lifecycle.
. |
| Purpose |
|
The Property Reinsurance System (PRS) described in this
document refers to a ‘replacement and re-engineering’ project
deployed for a Fortune 500 company over a 12-month period from October
2000 to October 2001. The purpose of this document is to determine some
best practices for applying a comprehensive testing strategy to an
iterative development project. The
project blended approaches of two leading, open methodologies, the
Rational Unified Process (RUP) and eXtreme Programming (XP).
One of the challenges discovered throughout the project was in
maintaining a disciplined testing schedule throughout a series of
back-to-back iterations. As
a large-scale web development effort dealing with a revenue generating
application, testing to ensure a robust and reliable application was
paramount. This document
describes key learnings and proposed solutions to integrating a rigorous
testing cycle into an iterative development project. |
| Property Re-Insurance System |
|
In October 2000, the customer, FedRe Inc.,
initiated the development of a new software application known as the
Property Reinsurance System (PRS).
The application was intended to be an object oriented, web based
application, which could provide real-time property re-insurance quotes
to FedRe customers. As part
of the development process, FedRe identified, as one of its
requirements, that a software development methodology known as the
Rational Unified Process (RUP) be used throughout the lifecycle of the
project. As the consulting
company responsible for delivering the project within a fixed time and
price contract the Rational Unified Process was also complemented by a
more recent methodology known as eXtreme Programming (XP).
PRS was intended to replace an existing
client-server application that had been developed in the early 1980s for
a specific customer and overtime had grown into a product used by a
large number of FedRe’s customers.
The project had several stated objectives and constraints:
1.
Develop a new version of PRS that was an n-tiered, web services
based application. Web services refer to exposing core application
services through an XML interface using an HTTP transport layer.
2.
Develop the system using a Microsoft toolset (Visual Basic 6.0,
ADO 2.5 and ASP 3.0) that fitted the stated architectural direction of
FedRe and its parent organization.
3.
Apply an iterative development process to the application based
on the Rational Unified Process (RUP) and eXtreme Programming (XP).
4.
Develop new functionality, not present in the current
client-server version of PRS, and examine re-engineering opportunities
in the process of developing the system.
Through the Rational Unified Process the project
was delivered in a series of iterations over four phases (Inception,
Elaboration, Construction and Transition). The project was a $3 Million
U.S. initiative with a twelve month development period and involved a
team of 11 full time members (one project manager, two system architects
and eight developers). Approximately
130 customers used the system generating more than $40 Million in
revenue per year. |
| Software Development Project
Frameworks |
|
Within the software development industry there are a
variety of different project methodologies for developing software
systems. An increasing trend in the industry has been the introduction
of an iterative approach to software development.
Iterative software development focuses on creating functional
components of software in short and consistent periods of time. These iterations focus on ensuring high levels of visibility
into the software development and provide greater flexibility for
changes to user requirements. There
are two primary methodologies representing two very different schools of
though that have achieved prominence in the management of software
development projects: |
| Rational Unified Process |
|
The Rational Unified Process[i]
(RUP) undeniably ranks among the leading software development processes
available today. RUP evolved from the pioneering work of the ‘Three
Amigos’ (Grady Booch, James Rumbaugh and Ivar Jacobson) who aligned
their individual efforts to develop an object oriented, visual modeling
process into a comprehensive approach with a common language, Universal
Modeling Language (UML) notation. Currently
supported by Rational Software Inc. the methodology is distributed on a
CD in HTML format and is tightly coupled with some of the leading object
oriented development tools such as Rational Rose and Requisite Pro.
RUP contains a wealth of information, including process roles,
activities, recommended artifacts and document templates.
RUP is described as a use-case driven,
architecture-centric, iterative and incremental methdology. Functional
requirements are captured in use cases that drive the development
process. Specified use cases drive the analysis & design and test
workflows. Use cases also drive the architecture, which in turn,
influences the selection of use cases.
This interplay between use cases and architecture evolves in the
context of an iterative and incremental process.
A project is divided into a series of iterations where the most
architecturally significant and/or technically complex use cases are
tackled initially. During early project iterations, some previous work may be
discarded but later iterations add a greater proportion of incremental
functionality.
The motivation for a process like RUP is based on
the argument that iterative processes reduce project risk.
Requirements that change over time are more easily incorporated
into an iterative process, and management gains greater visibility into
the current status of the project. Project cost is reevaluated at the
end of each iteration. By focusing on essential requirements first, a
functional system can be delivered sooner with deferral of lower
priority functionality to subsequent releases.
As seen in Figure 1, RUP is composed of four
phases and nine core workflows. The
phases are Inception, Elaboration, Construction and Transition. The workflows are Business modeling, Requirements, Analysis
and Design, Implementation, Test, Deployment, Configuration & change
management, Project management, and Environment. Phases are subdivided into iterations during which the
workflows are performed. Each
iteration essentially applies the core workflows in what could be
constituted a mini-waterfall process. So RUP can be viewed as a
succession of short waterfall processes during which a system is built
incrementally. Scott Ambler
aptly describes this type of process as serial in the large-scale and
iterative in the small-scale[ii].
Figure 1 - Rational Unified Process

During the Inception phase the project scope is
defined and the business case is justified.
High-level use cases are developed for the system’s primary
functional requirements. Project
management tasks include conducting an initial risk assessment, and
estimating resources, schedule and overall cost.
During Elaboration, the problem domain is
subjected to detailed analysis and the architectural foundation is
established. A
supplementary specification is developed for non-functional
requirements.
In the Construction phase, the detailed design is
realized and implemented iteratively.
The objective is to produce a functional system by the end of
each iteration. Supporting
documentation is also developed iteratively.
The Transition phase results in the delivery of
the system to the user community. This
commonly occurs after a beta release has been tested by end users and
debugged.
RUP’s strengths lie in its foundation as an
iterative process that is requirements driven and architecture-centric.
A working system is delivered at the end of each iteration, which
act as important control gates on the progress of the project.
The process is extensively documented; all model artifacts are
based on UML, and supported by a suite of automated tools.
It is a robust process framework that can be tailored to project
needs.
Nevertheless, there are deficiencies in RUP.
Ambler notes that it is essentially a single-project development
process. It fails to
consider enterprise-level, multi-project issues. As a result,
application architectures may fragment across the enterprise and
opportunities for software reuse may be lost.
It does not address the post-Transition phase concerns of
operational support and maintenance, which over a system lifetime
probably consume more total resources than initial development. Since it
is based on UML, non-UML model artifacts are not covered and the process
documentation can consume expensive resources.
In Ambler’s opinion, the marketing of Rational’s commercial
tools dominates the process. Other
weak areas include metrics, testing and the crucial area of human
resource management.
Hesse’s criticisms of RUP are more fundamental[iii].
He argues that phases, which are a holdover from the classic
waterfall process, are not an appropriate structuring concept for Object
Oriented projects. Instead,
process activities and iterations should be linked to architecturally
significant milestones. Workflow
is an overloaded term and its relationship to phases is unnecessarily
complex. RUP lacks
high-level support for structuring complex processes such as hierarchy,
recursion and orthogonality. RUP
should be decomposable into sub-processes.
There is inadequate support for project management and
roles/interactions of project groups, especially in the area of user
feedback.
In addition to these criticisms, RUP also lacks
detailed advice on the Implementation workflow.
Since coding is arguably the most important project activity, a
software development team needs comprehensive guidance on how to most
efficiently manage the actual coding of the system.

[i]
Jacobson, Ivar, Booch, Grady and Rumbaugh, James, The
Unified Software Development Process, Reading, MA:
Addison-Wesley, 1999.
|
| eXtreme Programming (XP) |
|
Kent Beck[i]
started XP about six years ago to develop a lightweight approach to the
‘high ceremony’ process of the RUP methodology.
This approach has been emulated by others including Alistair
Cockburn’s Crystal family of methodologies[ii],
Jim Highsmith’s Adaptive Software Development[iii],
SCRUM[iv],
Scott Ambler’s Agile Modeling[v].
More recently, the leading proponents of lightweight
methodologies have formed the Agile Alliance, an umbrella organization
that promotes the principles of lightweight processes.
A growing number of websites, magazine articles, books and
conferences devoted to agile methods attest to their current popularity
among programmers.
XP promises a high level of customer satisfaction
based on four process principles: communication, simplicity, feedback
and courage. To gather
requirements, it supports communication within a development team that
includes client staff, and it encourages the use of the simplest design
and implementation that meets those requirements.
Feedback is obtained through extensive unit testing during each
iteration. In fact, unit tests should be written prior to actual coding.
With this foundation of teamwork, simplicity, and automated testing, XP
claims that developers have the courage to respond to unexpected
requirements changes.
It’s probably more accurate to classify XP as a
collection of practical programming techniques than a complete software
development process. Figure
2 depicts the process flow for an XP project.
Requirements are captured in user stories, which are essentially
high-level use case descriptions without detailed, step-by-step
functional details. The
XP website provides the following description of user stories:
User stories serve the same purpose as use cases but are not the same.
They are used to create time estimates for the release planning meeting.
They are also used instead of a large requirements document. User
Stories are written by the customers as things that the system needs to
do for them. They are similar to usage scenarios, except that they are
not limited to describing a user interface. They are in the format of
about three sentences of text written by the customer in the
customer’s terminology without techno-syntax.
Figure 2 - eXtreme Programming (XP)
As Figure 2 shows, each iteration is preceded by
a Release Planning activity that describes the work to be done based on
the following inputs: requirements (User Stories), high-level
architectural analysis (Architectural Spike) and throw-away programs
that explore particularly difficult areas (Spikes).
The iteration proceeds after confident estimates are obtained and
the code is debugged until it passes all acceptance tests.
The result of an iteration is the release of a functional
sub-system. Eventually,
the complete system is developed through this iterative process.
XP is an iterative process designed for small
(2-12 person) teams. Developers,
who work in pairs, write unit tests prior to writing the actual code and
they review each other’s code. The
code should be the simplest possible implementation of the requirements
and it should be refactored
repeatedly.
In reaction to heavyweight processes that have an
elaborate management structure and produce extensive documentation
artifacts, XP deliberately minimizes these process activities. Project management is viewed as inefficient bureaucracy, and
code is regarded to be the only documentation that is inherently
reliable. These policies are justified with claims that modern software
development, especially internet applications, can not be developed with
heavyweight processes when requirements are unpredictable and delivery
timeframes are short.
XP’s strength is its unflinching focus on
getting the code written so that each iteration yields a functional
product. It is a hands-on approach driven by developers with direct
client involvement to foster communication, much of which is informal.
Product quality is achieved through pair programming and
automated unit testing.
XP does have limitations.
Like RUP, it is not an enterprise process. In fact, its focus is really in RUP’s construction phase
where code is being planned and implemented.
The claim that pair programming is more productive is debatable.
It does not provide clear guidance on what models or documentation
artifacts should be developed. With
minimal management and documentation activities, the ability of XP to
scale to enterprise level projects is questionable. XP also has the
potential to make the support and maintenance of a system difficult with
its lack of emphasis on formal documentation.


[i]
Beck, Kent, Extreme Programming Explained-Embrace Change,
Addison-Wesley, 2000.
[ii]
Cockburn, Alistair, Agile Software Development: Software
through People, Addison Wesley Longman Inc, December 2001.
[iii]
Highsmith, James A III, Adaptive Software Development: A
Collaborative Approach to Managing Complex Systems, Dorset House
Publishing, December 1999.
[iv]
Schwaber, Ken and Beedle, Mike, Agile Software Development
with Scrum, Prentice Hall PTR, October 2001.
|
| Testing Within Methodologies |
|
Both RUP and XP include a heavy focus on testing
throughout their methodology framework.
Within RUP a test workflow exists that provides an activity
diagram that illustrates how to develop and support a test management
strategy for all elements within the project.
XP focuses on testing more at the unit level and is based on the
assumption that no code can be released until it has passed its basic
unit tests.
Within RUP, the testing workflow mirrors the
development workflow (Figure 3) with increasing amounts of testing
activity as the project moves through the Elaboration and Construction
phases. Interestingly, the
amount of testing effort is seen to decrease in the Transition phase
even though the RUP process supports regression testing
throughout its lifecycle. RUP
provides an excellent overview of the testing process including key
concepts such as coverage measures (both code and requirements) and
quality measures (such as defect tracking and trend analysis).
Figure 3 - RUP Implementation and Test
Workflow

Both XP and RUP emphasize the need for automating
testing particularly for regression testing of the application (testing
all test cases with the release of a new iteration).
RUP uses the concept of a test case to validate functional
testing of the system which is developed from the use cases documenting
system functionality. XP bases its testing structure on acceptance tests
(formerly known as functional tests) which capture ‘black box’ test
results (validating external outputs not internal component testing of
code). XP advocates creating acceptance tests from user stories that
are similar to RUP’s use cases but are shorter (typically “three
sentences of text written by the customer”). However, XP does not
provide any guidelines on managing the testing sequence beyond the code
level and its primary emphasis on managing and correcting defects is
with the developers. Developers
are tasked with the responsibility of scheduling time each iteration to
correct defects, which are based on acceptance test scores.
XP lacks the holistic approach to testing that the RUP
methodology provides and does not go into the detail on the
organizational alignment required for the project.
The one most significant deficiency of both RUP
and XP regard their defect correction from a previous iteration within a
current iteration. As the
remainder of this paper will illustrate, managing defects within an
iterative process become one of the most complex elements of a project.
The challenge lies in ensuring that defects identified outside of
the tests executed by developers (during User Acceptance testing for
example) can be adequately factored into the development cycle and
corrected.
|
| The FedRe Example |
|
There are some particularly challenging aspects
of iterative processes that should be noted. A commonly touted advantage
is that iterative processes avoid the unpredictably long testing period
at project end that are seen in waterfall development methodologies. Admittedly, it is less expensive to correct a defect early in
the project than later. Nevertheless,
testing remains a major resource commitment that continually threatens
the project schedule. In
the PRS project even with automated unit testing, it was very difficult
for the developers to finish the iteration build in time for adequate
integration testing particularly with regression testing.
In the PRS project, developers were scheduled to
deliver a build early in the final week of the iteration. The analyst/architect then performed integration testing.
Bugs were logged in a Lotus Notes database and the developers
fixed bugs generating a new build at least daily. This cycle was
repeated until Thursday afternoon at which time the system was frozen
for the Friday demo to the client.
Unfortunately due to the ambitious workload, the initial build
was often delivered later in the week.
This prevented the analyst/architect from conducting thorough
testing, and the developers did not have enough time to fix all the
bugs. Although the primary
functionality of the system was available at the end of each iteration
(as represented through the basic flow of each use case) a number of
known defects were present in the build as it was delivered to the
client’s QA department.
As a result, it was not possible to achieve the
level of stability required and some known bugs were carried over to the
next iteration. This
ongoing deferment of bug fixes to later iterations became a major
impediment and resulted in a longer than planned stabilization period
after iteration nine. To
some degree this necessitated an iteration ten, although this was also a
reflection of a significant architectural change associated with an
off-site hosing service. We
feel this problem can be partially addressed by automated integration
testing. To successfully
use automated testing, it is crucial that the GUI be stabilized as early
as possible. Unfortunately,
this was not possible because the usability expert joined the project
very late resulting in extensive revisions to the GUI.
Another mitigating technique is to schedule a
buffer period for extra testing periodically throughout the project, a
practice employed by Microsoft[i].
The idea is to designate certain iterations as major release
points which are allotted an extra period of time to stabilize the
application with extra testing. We
believe that inserting a buffer period after every third iteration, for
example, is merited given the scheduling challenges. For a one-month iteration, we recommend a buffer period of at
least one week.
Within FedRe, the client had already developed a
formal testing methodology that had been applied to a series of
completed projects, primarily waterfall based development efforts.
Prior to deployment, applications required ‘certification’
from the Quality Assurance Department, which acted as an independent and
objective testing group for all applications.
Due to the sensitive nature of the PRS application, testing was
seen as a critical component of the overall project plan.
The challenge then became how to integrate the
testing captured by the application development team in its iterative
development cycle and appropriately blend it with an independent testing
group. To further compound
matters, the independent testing group had a strong desire to be more
actively involved in the full project lifecycle, specifically the
Inception, Elaboration, Construction and Transition phases.
This meant applying their testing structure to each completed
iteration. However, the testing group was more familiar with a waterfall
development approach that provided greater application functionality and
much more stable code base when they applied their testing.
In addition, agile development techniques
advocate developing a unit test framework that provide good code level
testing and help manage. However,
this testing approach is not exhaustive, particularly for functional and
system level testing. While
the Rational Unified Process provides a more comprehensive overview for
testing, it is deliberately high level and requires more
‘real-world’ grounding. The
remainder of the document describes how to integrate testing across both
methodologies and how to align it with an independent testing group.

[i]
Cusumano, Michael and Selby, Richard, Microsoft Secrets,
New York, NY: Free Press, 1995
|
| Defining A Framework |
|
To successfully apply a testing framework within
an iterative development project it is important to explicitly document
what you want to test and determine who is going to do the testing.
To help align the testing of the PRS project and make it more
explicit to the project stakeholders (which included their Internal
Audit department), a comprehensive Test Plan was developed that
encapsulated all testing within the system.
While this artifact was similar to the product identified in the
Rational Unified Process it was focused more on showing testing as a
separate workflow within the application development and it collapsed
many of the test types into more manageable groupings. The purpose of
application testing was:
·
To verify the interaction between objects.
·
To verify the proper integration of all components of the
software.
·
To verify that all requirements have been correctly
implemented.
·
To identify and ensure defects are addressed prior to the
deployment of the software
The Test Plan acted as a Master Guide to testing
within the PRS project and it in turn supported the details of Test Type
Plans developed to capture all of the testing requirements of the
application. Conceptually,
the Test Plan can be seen in the following way:
The test type plans contained the actual details
on the tests developed for the system.
This documentation was used for regression testing of application
fuctionality and for automation of testing using tools.
While the Unit tests advocated in XP provide good white box
(structural) testing at the code level these still need to be
complemented by black box (functional tests) and appropriate component
level testing.
Within the PRS Project specific testing areas
that were be addressed included Functional Tests (driven by use
cases), User Interface Tests (driven by User Interface Design
Standards), Performance Tests (load, stress and performance
related), Data Integrity Tests and Security Tests.
Developers are still required to create unit tests and these
tests must be successfully passed before being integrated.
While developing a test plan of this nature might feel like a lot
of work, the payoff is knowing that your testing the application from a
variety of perspectives.
As Steven Splaine states in his Web Testing
Handbook[i]
In
our experience, the easiest way to plan (or design) the testing of a Web
site/application is to develop a series of Test Plans. These plans help
ensure that the Web site/application is comprehensively tested and can
be reliably re-tested. Each test plan is focused on a different phase of
the testing process (e.g., unit testing, system testing, or
post-implementation testing), while the individual test cases within
each test plan are grouped into categories that focus on a single aspect
of testing.

[i]
Splaine, Steven et al. The Web Testing Handbook, New
York: New York, McMillan Publishing, 2000
|
| Testing Layers |
|
The testing lifecycle is an integral part of the
software lifecycle; they should start at the same time. The design and
development process for tests is as complex and arduous as the
application being built. If not started early enough, the tests will
either be deficient, or cause a long testing and bug-fixing period to be
appended to the development schedule, which defeats the goals of
iterative development. Furthermore, the test planning and design
activities can expose faults or flaws in the application design. The
earlier these are resolved the lower the impact on the overall schedule.
Problems found during evaluation can be solved within this iteration, or
postponed to the next iteration. To
address these challenges it is important to test in layers.
The test plan for the PRS project consisted of
four primary testing layers: Coding,
Integration, Quality Assurance and User Acceptance Testing.
Each of these layers progressively built upon the other to ensure
as many defects as possible had been discovered and corrected.
Since test details for the PRS project were all use case driven
they reflect traceability from use cases to the design model to the test
cases of the system. The details of the testing are as follows:
Development
Level Testing: The development of the application used a Unit
Test Framework to ensure that at least 50% of the bugs present in the
application were captured and corrected prior to moving the code to the
next level of testing. The
Unit Test Framework was developed by implementers throughout the
development effort of each iteration. Unit tests are automated tests
that verify the internal structure of methods and validate the expected
results that these methods are to provide.
Designing unit tests allows the code in the application to be
frequently tested and makes it easier to provide regression testing
throughout the life of the project.
As advocated by Karlson, Andersson and Leion, the
developers had their own private environment where the builds and
testing could occur prior to submitting to the integration environment.
As the authors recommend the PRS project followed “a code
review, compile, load and some form of regression test before submitting
the code. The full
regression test of old functionality is completed centrally”[i].
Unit tests focus on small testable elements of
the software that independently might not provide appropriate testing
coverage but used in conjunction with one another provide
decision-to-decision path testing for the entire application.
All unit tests had to be passed before code was
released.
Integration
Testing: Integration testing involves the creation of a test
matrix and related test cases to test the functionality of groupings of
classes and methods. The
integration testing was conducted by the Architect, System Analyst and
Code Reviewer of the project and followed a use case flow with a
standard set of inputs and expected outputs.
This level of testing was completed before the demo held at the
completion of each iteration. At
this point it was estimated that approximately 80% of the bugs present
in the system were corrected but 100% of the documented functionality is
available for testing.
Quality
Assurance Testing: After integration testing, the PRS
application was migrated to the independent testing area in the
customer’s Quality Assurance department.
This level of testing was conducted in a separate physical
environment from the development environment. At this level of testing,
integration between use cases was tested and non-functional testing such
as load testing, stress testing and security testing was conducted.
Defects discovered from this testing were provided to the
development team for inclusion in the upcoming iteration.
At the completion of QA testing 90% of the system bugs should be
corrected.
User
Acceptance Testing: Once the system has satisfactorily passed
the previous three levels of testing it was moved into a separate
physical environment for User Acceptance Testing.
This type of testing was typically performed prior to releasing
the system into production and it involves system users developing and
executing their own test cases to validate the functionality of the
system. Oftentimes, system
users require assistance in developing these test cases and in following
through on their execution. This
assistance was provided to staff through the development of templates
and in direct mentoring and support.
This form of testing is similar to that promoted
by the Department of Defense[ii]
which describes three levels of tests; low level, software integration
and hardware/software integration.
Figure 4
- Testing Phases
As Figure 4 shows the different phases of testing
(Development, Quality Assurance and User Acceptance) all added
incremental amounts of time to the testing process.
This was particularly influenced by the waterfall nature of the
testing that the client required QA
would not begin testing until development testing was completed and User
Acceptance testing was not allowed to begin until QA testing was
completed.

[i]
Karlsson, Even-Andre, Andersson, Lars-Goran and Leion, Per, Daily
Build and Feature Development in Large Distributed Projects,
Limerick, Ireland. ICSE Publishing, 2000
[ii]
RTCA/DO178B, Software Considerations in Airborne Systems
and Equipment Certification, TRCA, Inc. 1992
|
| Managing Defects |
|
Probably one of the biggest challenges posed by
an iterative development process is the task of managing defects.
Defects are a natural result of software development and the key
to effective software development is ensuring that these defects are
captured and corrected before moving an application into production.
However, testing needs to occur at much more than just the
developer and code level. Users
need to apply their own testing to an application and using an
independent testing assessment also offers greater testing coverage to
an application. Unfortunately,
the challenge of managing defects with a series of back-to-back
iterations can be particularly challenging.
Neither RUP nor eXtreme Programming offers much
insight into managing defects throughout a project with a large number
of scheduled iterations. The
challenge that rapidly becomes apparent is how to schedule defect
correction within a defined iteration.
The best way to illustrate this is through an
example. The PRS project
approached the project as a series of nine iterations (Figure 5). An
iteration routemap (a tool that prioritizes uses cases based on
complexity and risk and maps these to successive iterations) was used to
identify functionality scheduled for each iteration.
Each iteration was four weeks long and progressively built on
functionality provided in the iteration previous.
Figure 5 - PRS Iteration Schedule

However, testing completed at the end of an
iteration consisted only of unit testing and integration testing (test
cases derived from use cases). This
testing did not permit adequate user testing which often identifies not
only functional defects but also functional omissions (requirements not
reflected in use cases). Once
the users and, also the independent testing group, were able to test the
application any new defects logged could only get addressed in the
current iteration (see Figure 4 for an illustration).
Unfortunately, even with the flexibility for requirements change
in an iterative schedule, most Severity One or Two defects discovered in
the last two weeks of an iteration had to be deferred to the following
iteration.
As a result, tracking the iteration in which a
defect was being corrected required significant coordination. The process also required good communication as users and the
independent testing team often had challenges in waiting upwards of two
months to see their defects get corrected.
This was in addition to the traditional challenge of
communicating to users that not all functionality for the system would
be available in each iteration and that this did not necessarily
constitute a defect.
The challenge became managing the feedback loop
from testers into the iterative schedule of the application developers.
Often Severity One defects (defects that prevented the system
from functioning) required an Architect to review and assess any design
changes that might be required. This further impacted the ability of architects to complete
analysis design on the iteration they were working on.
Figure 6 - Defect Testing Cycle
|
| Learnings |
|
Define a Test Strategy
Creating a Test
Strategy to define what should be tested and who should perform the
testing is critical to developing a thorough testing approach for an
application. The RUP test
plan artifact is a good starting point for developing an overall
strategy. The Unit tests
advocated in XP provide good white box (structural) testing at the code
level, however, these still need to be complemented by black box
(functional tests) and appropriate component level testing.
Within the PRS project the test plans identified testing for
several key areas common in most application development projects:
Functional Tests (driven by use cases), User Interface Tests (based on
User Interface Design standards), Performance Tests (load, stress and
performance related), Data Integrity Tests and Security Tests.
Developers are still required to create unit tests and these
tests must be successfully passed before being integrated., however
these additional test ensure the application is thoroughly tested before
deployment.
Test In Layers
Both RUP and XP place a
great deal of emphasis on the developers to test the application.
This makes sense from the perspective that they know the code and
they should be responsible for fixing their own mistakes. However, it is important to have different groups with
different motivations testing the application.
On larger projects, a Quality Assurance group separate from the
development group should test the application, particularly the
‘system components’ (data integrity, security, performance tests).
A User Acceptance group should test the application primarily
from a functional and user interface perspective.
Having developers focus on code level testing, QA focusing on
system testing and users focusing on whether the functionality meets
their needs should help identify most defects before the system moves
into production.
The Test Coordinator
A critical role within
an iterative development project is a Test Coordinator.
This role, which might be full or part-time, needs to keep on top
of what has been tested and what defects are outstanding.
This role is usually a good one to advocate testing automation
and the person in the role should be both a strong developer and well
organized. The testing coordinator also needs to help the project
manager understand the real state of the application (architects and
lead developers are often too close to the application to offer accurate
assessments). The testing
coordinator should be responsible for reviewing and assessing all of the
defects in the defect tracker used each day.
The coordinator should work closely with the architect to
determine if a defect really exists or if it reflects functionality that
will be built in an upcoming iteration (since only partial functionality
is available at the end of each iteration since the application is
incrementally developed over the lifecycle of the project).
The coordinator needs to also work closely with those who sourced
a defect to ensure they re-test it prior to closing it.
It’s not uncommon to have an individual enter a number of
defects but not close them after they’ve been corrected, the
coordinator needs to ensure that defects are well managed otherwise the
defect log can become overwhelming. Finally, the testing coordinator needs to actively ensure
that tests are regressed frequently throughout the lifecycle of the
project. Many projects
start short changing full regression testing in order to save time near
the end of a project. While
there might be some ‘balancing’ required between full regression
testing and meeting project deadlines, the test coordinator should
ensure that tests are at least alternated between iterations, that a
full regression test is applied every three iterations and that test
cases are prioritized so more complex functionality is tested
frequently.
Testing Buffers Between
Iterations
One of the primary
differences between an iterative development approach and a traditional
waterfall development approach is that there is less risk of a
disconnect between requirements and functionality.
This is because the period between gathering requirements and
provisioning functionality is shorter in an iterative development
project. However, one of
the advantages of the waterfall approach was that it provides for
‘level sets’ which allows functional components of software to be
thoroughly tested before moving to the next stage of development. From
the experience of the PRS project it is suggested that a blend of
approaches might reflect a software development “Best Practice”. The proposed solution is to provide a defect correction
buffer at the completion of every two or three iterations. This allows development to continue rapidly while also
periodically ensuring that it does not get too far ahead of itself
leading to greater rework in the future.
Using Automated Test Tools
Iterative development
places a heavy emphasis on automation.
One significant advantage of an iterative development project is
that each iteration provides an opportunity to regress through all
tests. This provides a
tremendous opportunity to thoroughly test high risk and high complexity
functionality (which should be loaded early into the iterations
schedule). However, testing
can rapidly become onerous if test cases are not automated. The challenge is that most GUI based testing tools are very
fragile in supporting iterative development projects due to the frequent
updates to the user interface. One
choice is to accept the extra testing effort required during initial
iterations and to manually document and execute tests though test cases
which can then be automated once the application is released into
production and the code base becomes stable.
Alternatively, the unit tests developed can include more
functional testing although this can run the risk of making these
lightweight tools difficult to manage. The approach adopted for the PRS project was to only develop
automated testing tools after the application had a release moved into
production.
|
| Conclusion |
|
The PRS project provided a real world example of the
challenges of integrated a testing framework into an iterative
development process. Following
the Rational Unified Process (RUP) and components of the eXtreme
Programming (XP) methodology, the PRS project developed an iterative
testing framework to support the iteration schedule developed for the
project. Through this
process a series of learnings were documented which included the
assignment of a Test Coordinator to validate test execution and
coordinate defect resolution throughout iterations, a testing buffer
between iterations to allow defect correction efforts to re-synchronize
with the development effort and an aggressive focus on automated testing
tools to fully support regression testing.
With the relative infancy of the iterative development process it
is understandable that a testing approach has not been adequately
developed to support this software development approach.
However, the experiences gleaned from the PRS project described
in this paper might provide future project managers an opportunity to
better support their own iterative development projects.
|
| About the Authors |
|
Bryan Campbell
Bryan Campbell is an Engagement Manager with Valtech
Inc., a software development company specializing in object oriented
developing using the Unified Process.
Mr. Campbell has spent more than 15 years in the information
technology industry across a wide range of disciplines ranging from
operations to enterprise architecture to software development.
Currently completing his MBA specializing in Information
Technology Management, Mr. Campbell has managed a series of large scale
IT projects including software development projects using iterative
development techniques. Mr.
Campbell has worked in a variety of industries including
Telecommunications, Utilities and Insurance.
He is the author of several articles on software development and
has presented at several conferences.
Dr. Glenn Ray
Glenn Ray is an Object Oriented analyst/architect
for Valtech Inc.. Mr. Ray
has also managed his own marketing and consulting company for 10 years.
He is a former adjunct professor of Investment Planning at Florida State
University and adjunct professor of computer science at Florida A&M
University. He has a B.S.
from Florida State, a M.S.E.S from Florida A&M and a Ph.D. from MIT.
He is also a graduate of the College for Financial Planning..
|
|
Publication in part or in whole, without
the authors' written permission is prohibited |
|